After months of holding their tongues on slowdowns that have attended the Ladd Landing Greenway project, Kingston City Council members let loose with a barrage of concerns at a work session on May 7.
Unfortunately, engineer Kent Olson of Vaughn and Melton was the only one present to field the complaints.
Olson was at the meeting as a fill-in for Danl Hall, the man who is actually the chief engineer on the project. Thus, he was unable to answer council’s sometimes-pointed questions as to why the project is experiencing difficulties.